Mumbai Metro Line 2B Nears Key Milestone as Final Girders Go Up
Reported by Kunal Bhatia (Senior Writer) Β· The Times of India Β·
Confirmed by a second source: The Indian Express

Girder Installation
Construction work on the Andheri-Bandra stretch of Mumbai Metro Line 2B is approaching completion, with the Mumbai Metropolitan Region Development Authority aiming to install the last three girders near ESIC Metro Station at Juhu Circle by November 18. This 7.53-kilometre Andheri West to Saraswat Nagar stretch is scheduled to open by March 31, 2027, though the launch might face delays until the monsoon due to pending tasks. Metro Line 2B has finished 75 percent of its civil and systems works overall. At Juhu Circle, workers are placing 20 precast prestressed concrete I-girders across five spans over a 150-metre distance between Metro piers EC29 and EC35. J Kumar Infraprojects is handling the civil construction on this stretch. Each girder measures 33 metres long, 1.22 by 2.25 metres in cross-section, and weighs 115 metric tonnes. Workers have already put up 17 of these girders, leaving three still pending.
Challenges and Ground Realities
Installing the remaining girders at Juhu Circle has proved difficult because of narrow road space on Gulmohar Road, continuous traffic, limited room to set up cranes, and close buildings. To get the work done with minimum traffic disruption, the authority has decided to erect the final girders at night through road closures near the station. Meanwhile, a broader Rs 10,986-crore project is building the 23.643-kilometre elevated corridor across the suburbs. On an 8-kilometre stretch planned to open next between Andheri and Khar, tracks are fully laid except for a crucial 185-metre gap. This missing track sits over a plot at Juhu Circle where two crumbling apartment blocks belonging to the Juhu Gulmohar Cooperative Housing Society stand. One resident in his mid-fifties still lives there in a building that blocks the path. The gap sits between DN Nagar and ESIC Nagar stations where the new line joins operational Line 2A. Because of this gap, workers cannot lay full tracks, put up overhead power poles, or start trial runs, holding up the stretch for at least eight months. Following the planned 2027 opening of the first section, the 10.03-kilometre Saraswat Nagar to Chembur section is scheduled to follow in 2028.
Context
Large urban infrastructure projects often face complex delays when clearing private properties and securing municipal approvals in densely populated cities. Land acquisition disputes and shifting project alignments frequently push back completion deadlines for mass transit networks. Commuters in suburbs like Vile Parle, Santacruz, and Khar continue to await better rail connectivity once these bottlenecks are resolved.
ExplainerWhy this matters
What Happened
Metro Line 2B in Mumbai has faced prolonged delays because a 185-metre track gap remains unbuilt over a private housing society plot at Juhu Circle, where a revised 2015 alignment brought the elevated corridor too close to residential buildings.
Why It Matters
Without this small connecting piece of track between DN Nagar and ESIC Nagar stations, the MMRDA cannot install overhead power lines, complete track laying, or run trial tests, delaying the opening of a major commuter link for residents in suburbs like Vile Parle and Santacruz.
What Happens Next
Authorities must resolve the ongoing land and safety zone disputes involving the remaining residents and buildings on the plot before the final track segment can be cleared and constructed.
More in Trending
TrendingVerified β Confirmed by a second source: Suryaa NewsImportant
Husband Vicky Kaushal brings peace amidst my busy life, says actor Katrina Kaif
Reported by Vivek Joshi (Copy Editor) Β· Eenadu Β·